Thirty men working at the rate of 10 hours a day can complete a job in 14 days. Find how long it would take 40 men working at the rate of 7 hours a day to complete the same job.

Class: Form 1

Subject: Mathematics

Topic: Rates, Ratios, Proportions and Percentages

Lesson Summary

Thirty men working at the rate of 10 hours a day can complete a job in 14 days. Find how long it would
take 40 men working at the rate of 7 hours a day to complete the same job.



Text Answer


q12132019606.png

Next: Kirui bought a suit for sh 1200 and marked it at a price such that after allowing his customer a 10% discount, he would make a profit of 20%. Calculate the marked price of the suit.
Previous: The surface area of two similar bottles is 12cm2 and 108cm2 respectively. If the larger one has a volume of 810cm3. Find the volume of the smaller one.

View all Form 1 Mathematics Video Lessons | View All Lessons

More Video Lessons


View all video lessons  
Kenyaplex Learning