Describe the concept of building the work breakdown structure

      

Describe the concept of building the work breakdown structure

  

Answers


Francis
1. Using guidelines: Some organizations, like the DOD, provide guidelines/requirements for preparing a WBS
2. The analogy approach: A WBS is first created by looking for a similar project done in the past and using its WBS as a starting point
3. The top-down approach: Start with the largest items of the project and keep breaking them down into smaller and smaller parts
4. The bottoms-up approach: Start with the detailed tasks and roll them up
5. Thread – concentrate on most important items first
francis1897 answered the question on March 13, 2023 at 10:33


Next: What are the functions of work breakdown structure?
Previous: What are the advantages of the approaches used in work breakdown structure?