List the five distinct aspects which the Project Manager should consider when preparing a project communications plan.

List the five distinct aspects which the Project Manager should consider when preparing a project communications plan.

Answers


Lydia
i. Stakeholder communications requirements
ii. Information to be communicated, including format, content, and level of detail
iii. Who will receive the information and who will produce it
iv. Suggested methods or technologies for conveying the information
v. Frequency of communication
vi. Escalation procedures for resolving issues
vii. Revision procedures for updating the communications management plan