Using the percentage of completion method, prepare the following in the books of Ujenzi contruction ltd i) Profit and loss account for each of the three...

On 1 January Ujenzi construction Ltd was awarded a contract for the construction of a road .The contract was for a three year period. The contract price was sh 250 million. The following information has been extracted from the books of the company
ujenzi411220191134.png

Answers


Wilfred
ujenzi111220191126.png
ujenzi211220191131.png
ujenzi311220191132.png
Wilfykil answered the question on February 11, 2019 at 07:35