Trusted by millions of Kenyans
Study resources on Kenyaplex

Get ready-made curriculum aligned revision materials

Exam papers, notes, holiday assignments and topical questions – all aligned to the Kenyan curriculum.

A project has 11 activities with the activities preceding constraints, time estimates and work team requirements as shown

A project has 11 activities with the activities preceding constraints, time estimates and work team requirements as shown
est12022019426.png

Required:
i) Prepare a network and indicate critical path.
ii) Prepare a time chart and work team requirement.
iii) Can the work team resource be levelled further? Why?

Answers


Wilfred
est22022019429.png
est32022019429.png
Wilfykil answered the question on February 20, 2019 at 12:30

Answer Attachments

Exams With Marking Schemes

Related Questions