Trusted by millions of Kenyans
Study resources on Kenyaplex

Get ready-made curriculum aligned revision materials

Exam papers, notes, holiday assignments and topical questions – all aligned to the Kenyan curriculum.

MMK Ltd. plans to conduct a survey. The following table shows the tasks involved, the immediately preceding tasks and for each activity duration the most...

MMK Ltd. plans to conduct a survey. The following table shows the tasks involved, the immediately preceding tasks and for each activity duration the most likely estimate (L), the optimistic estimate (O) and the pessimistic estimate (P).
mmk12022019257.png

Required:
a) Compute the mean duration and standard deviation for each task
b) The project is budgeted to cost Sh.500,000. Actual costs per day are Sh.10,000. By first identifying the critical path from drawing a network diagram can the project be implemented within the budget.
c) What is the probability of finishing the project 4 days earlier than the expected duration?

Answers


Wilfred
mmk22022019305.png
Wilfykil answered the question on February 20, 2019 at 11:05

Answer Attachments

Exams With Marking Schemes

Related Questions