How long would five men working 4 hours a day take to dig a trench 45 m long?

Three men working for 8 hours a day take 6 days to dig a trench 9 m long. How long would five men working 4 hours a day take to dig a trench 45 m long?

Answers


Raphael
Men---Hours---Days---Length
3--------8-------6------9
5--------4-------x------45

$x=6 \times \frac{3}{5} \times \frac{8}{4} \times \frac{45}{9} = 36 \ days$