A contractor employed 60 men to complete a piece of work in 150 days. How many more days would 50 men take to complete the same...

A contractor employed 60 men to complete a piece of work in 150 days. How many
more days would 50 men take to complete the same work?

A.180
B.30
C. 40
D. 50