A contractor was to finish a piece of work in 80 days. He employed 150 workers to work for 6 hours a day.

A contractor was to finish a piece of work in 80 days. He employed 150 workers to work for 6 hours a day. After 30 days he found out that only a quarter of the work had been done. How many more workers did he require to finish the work in time

Answers


Wilfred
q10492019852.png
Wilfykil answered the question on September 4, 2019 at 05:53