Explain the following terms used in network analysis: i) Network planning; ii) Activities; iii) Events; iv) Critical path; v) Float.

Explain the following terms used in network analysis:
i) Network planning;
ii) Activities;
iii) Events;
iv) Critical path;
v) Float.

Answers


Wilfred
i) Network planning is the arrangement of activities and events in a diagram to create a logical relationship from start to end making up a project.
ii) Activities are those actions that take up resources and time.
iii) Events indicate start or completion of activities
iv) Critical path is a combination of activities that, if any of them is delayed, then the projects duration will also delay. That is, they are critical to the projects duration. They are activities with zero floats.
v) Float is the amount of time an activity can be delayed without delaying the overall time of the project.
Wilfykil answered the question on February 20, 2019 at 07:18

Answer Attachments

Exams With Marking Schemes

Related Questions

  • Consider a project which has been modeled as follows: Required: a) Determine the project?s expected completion time and its critical path. b) Can activities E and G be... (Solved)

    Consider a project which has been modeled as follows:
    proj120220191111.png

    Required:
    a) Determine the project‟s expected completion time and its critical path.
    b) Can activities E and G be performed at the same time without delaying the completion of the project?
    c) Can one person perform activities A, G and I without delaying the project?
    d) By how much time can activities G and L be delayed without delaying the entire project?
    e) By how much time would the project be delayed if activity G were delayed by 3 hours and activity L by 4 hours? Explain.

    Date posted: February 20, 2019 .    Answers (1)

  • Consider the cost-time estimates for the product development project as given in the table below. (Solved)

    Consider the cost-time estimates for the product development project as given in the table below.
    ct120220191103.png

    Indirect cost is made up of two components: Fixed cost of $5,000 and a variable cost of $1,000 per week of elapsed time. Also, for each week the project exceeds 17 weeks, an opportunity cost of $2,000 per week is assessed.

    Construct a time chart for the minimum total cost schedule.

    Date posted: February 20, 2019 .    Answers (1)

  • Consider the simplified scenario for the development of a consumer product through the market test phase shown in the table below. (Solved)

    Consider the simplified scenario for the development of a consumer product through the market test phase
    shown in the table below.
    pdt120220191050.png

    a) Draw the network for this project.
    b) Calculate the slacks and interpret their meaning.
    c) Determine the critical path and interpret its meaning.
    d) Construct a time chart and identify scheduling flexibilities

    Date posted: February 20, 2019 .    Answers (1)

  • Consider the two person zero sum game between players A and B given by the following pay-off table: (Solved)

    Consider the two person zero sum game between players A and B given by the following pay-off table:
    zerosum23120191154.png
    Required:
    i) Using the maximin and minimax values, is it possible to determine the value of the game? Give
    reasons.
    ii) Use graphical methods to determine optimal mixed strategy for player A and determine the
    value of the game.

    Date posted: January 23, 2019 .    Answers (1)

  • Define the following terms used in game theory: i) Dominance. ii) Saddle point iii) Mixed strategy iv) Value of the game (Solved)

    Define the following terms used in game theory:
    i) Dominance.
    ii) Saddle point
    iii) Mixed strategy
    iv) Value of the game

    Date posted: January 23, 2019 .    Answers (1)

  • Explain the following terms as used in decision analysis. a) Decision making under risk versus uncertainty. b) Decision trees versus probability trees. c) Minimax versus maximax criterion. d) Pure... (Solved)

    Explain the following terms as used in decision analysis.
    a) Decision making under risk versus uncertainty.
    b) Decision trees versus probability trees.
    c) Minimax versus maximax criterion.
    d) Pure strategy versus mixed strategy games.
    e) Games with more than two persons versus non zero-sum games

    Date posted: January 23, 2019 .    Answers (1)

  • An urban cable television company is investigating the installation of cable TV system in urban areas. The engineering department estimates the cost of the system... (Solved)

    An urban cable television company is investigating the installation of cable TV system in urban areas. The engineering department estimates the cost of the system (in present worth Sh.) to be Sh. 7 million. The sales department has investigated four pricing plans. For each pricing plan, the marketing division has estimated the revenue per household in present worth Sh. to be:
    urbancable23120191143.png

    Date posted: January 23, 2019 .    Answers (1)

  • A trust officer for a major banking institution is planning the investment of a USD 1 million family trust for the coming year. The trust... (Solved)

    A trust officer for a major banking institution is planning the investment of a USD 1 million family trust for the
    coming year. The trust officer has identified a portfolio of stocks and another group of bonds that might be
    selected for investment. The family trust can be invested in stocks or bonds exclusively, or a mix of the two.
    This trust officer prefers to divide the funds in increments of 10 percent; that is, the family trust may be split
    100 percent stocks /0 percent bonds, 90 percent stocks /10 percent bonds, 80 percent stocks /20 percent
    bonds, and so on.
    The trust officer has evaluated the relationship between the yields on the different investments and general
    economic conditions. Her judgment is as follows:
    1) If the next year is characterized by solid growth in the economy, bonds will yield 12 percent and stocks
    20 percent.
    2) If the next year is characterized by inflation, bonds will yield 18 percent and stocks 10 percent.
    3) If the next year is characterized by stagnation, bonds will yield 12 percent and stocks 8 percent.
    a) Formulate a payoff table where payoffs represent the annual yield, in dollars, associated with the
    different investment strategies and the occurrence of various economic conditions
    b) Determine the optimal investment strategy using the max-max, max-min, Hurwicz (alpha23120191129.png),
    equally likely, and regret criteria.
    c) Suppose that a leading economic forecasting firm projects P(solid growth)= 0.4, P(inflation)=0.25,
    and P (stagnation)= 0.35. Use the expected value criterion to select the appropriate strategy.
    d) What is the expected value with perfect information?

    Date posted: January 23, 2019 .    Answers (1)

  • The following table is a payoff table for a particular venture. (Solved)

    The following table is a payoff table for a particular venture.
    payoff23120191121.png
    Required:
    a) Determine the decision alternative that maximizes expected payoff.
    b) Determine expected value under certainty.
    c) What is the expected value of perfect information?

    Date posted: January 23, 2019 .    Answers (1)

  • The following is a payoff table for a particular venture. (Solved)

    The following is a payoff table for a particular venture.
    playoff2312019923.png
    Determine the optimal decision using:
    a) Max-min criterion.
    b) Max-max criterion.
    c) Min-max regret criterion.
    d) Maximum expected payoff (assuming equal likelihood of states of nature).

    Date posted: January 23, 2019 .    Answers (1)

  • Kenya Canning Transport is to move goods from three factories situated in Thika, Naivasha and Machakos. These goods will be distributed to Nairobi, Mombasa and Kisumu.... (Solved)

    Kenya Canning Transport is to move goods from three factories situated in Thika, Naivasha and
    Machakos. These goods will be distributed to Nairobi, Mombasa and Kisumu. Information about the
    units (in kilograms) to be moved is given below:
    kenyacanning1412019949.png
    Required:
    i) Draw a network diagram for the above problem
    ii) Set a linear programming model for this problem
    NOTE: Do not solve.

    Date posted: January 14, 2019 .    Answers (1)

  • The TamuTamu products company ltd is considering an expansion into five new sales districts. The company has been able to hire four new experienced salespersons. Upon... (Solved)

    The TamuTamu products company ltd is considering an expansion into five new sales districts. The
    company has been able to hire four new experienced salespersons. Upon analysing the new
    salesperson's past experience in combination with a personality test which was given to them, the
    company assigned a rating to each of the salespersons for each of the districts .These ratings are as follows:
    tamutamu1412019930.png
    The company knows that with four salespersons, only four of the five potential districts can be covered.
    Required:
    i) The four districts that the salespersons should be assigned to in order to maximize the total of the
    ratings
    ii) Maximum total rating.

    Date posted: January 14, 2019 .    Answers (1)

  • a) A baker makes two products; large loaves and small round loaves. He can sell up to 280 of the large loaves and up to 400... (Solved)

    a) A baker makes two products; large loaves and small round loaves. He can sell up to 280 of the large
    loaves and up to 400 small round loaves per day. Each large loaf occupies 0.01m3 of shelf space, each small loaf occupies 0.008m3 of space, and there is 4m3 of shelf space available. There are 8 hours available each night for baking, and he can produce large loaves at the rate of 40 per hour, and small loaves at the rate of 80 per hour. The profit on each large loaf is Sh.5.00 and Sh.3.00 profit on the small round loaf.
    Required:
    In order to maximize profits, how many large and small round loaves should he produce?
    b) Summarize the procedure for solving the kind of quantitative technique you have used to solve part (a) above.

    Date posted: January 11, 2019 .    Answers (1)

  • A company wishes to purchase additional machinery in a capital expansion program. Three types of machinesare to be purchased: A, B, and C. Machine A... (Solved)

    A company wishes to purchase additional machinery in a capital expansion program. Three types of machines
    are to be purchased: A, B, and C. Machine A costs USD 25,000 and requires 200 square feet of floor space for its
    operation. Machine B costs USD 30,000 and requires 250 square feet of floor space. Machine C costs USD 22,000 and
    requires 175 square feet of floor space. The total budget for this expansion program is USD 350,000. The
    maximum available floor space for the new machines is 4,000 square feet. The company also wishes to
    purchase at least one of each machine.
    Given that machines A, B, and C can produce 250, 260, and 225 pieces per day, the company wants to
    determine how many machines of each type it should purchase so as to maximize daily output (in units) from
    the new machines.
    a) Explicitly define your decision variables and formulate the LP model.
    b) Assess the validity of the four underlying LP assumptions for this problem.
    c) Solve and analyse the problem using a computer package

    Date posted: January 11, 2019 .    Answers (1)

  • Solve the following problem using the simplex method: (Solved)

    (a) Solve the following problem using the simplex method:
    simplex1112019759.png
    b) Verify your solution by solving graphically and relate tableaux to specific corner points.
    c) Determine the shadow prices and interpret their meaning.

    Date posted: January 11, 2019 .    Answers (1)

  • The number of plumbing repair jobs by Manji Plumbing Service in each of the last nine months in Nakuru town are listed below: Month---Jobs March 353 April 387 May 342 June... (Solved)

    The number of plumbing repair jobs by Manji Plumbing Service in each of the last nine months in
    Nakuru town are listed below:
    Month---Jobs
    March 353
    April 387
    May 342
    June 374
    July 396
    August 409
    September 399
    October 412
    November 408
    Required:
    Required:
    a)
    i) Forecast the number of repair jobs Manji Plumbing Service will perform in December. Use the
    least squares method.
    Note:
    manji1112029752.png
    ii) What is your forecast for December using a three-period weighted moving average with weights of
    0.6, 0.3, and 0.1. How does it compare with your forecast from part (i)
    above? b)
    i) What are the aims of time series analysis?
    ii) Describe what a season is in the context of a time series and give some examples.
    iii) Describe the stages in obtaining a time series trend using the method of semi averages.
    iv) Why must forecasts be treated with caution?

    Date posted: January 11, 2019 .    Answers (1)

  • Find the moving average of the time series of quarterly production (in tons) of coffee in an Indian State as given below. After that, come... (Solved)

    Find the moving average of the time series of quarterly production (in tons) of coffee in an Indian State as given below. After that, come up with a trend line to approximate the production in future.
    Production (in Tons)
    movingaverage1112019.png

    Date posted: January 11, 2019 .    Answers (1)

  • The following regression equation was calculated for class of 24 CPA II students. Required: a) Calculate the t ratio and the 95% confidence interval for each regression... (Solved)

    The following regression equation was calculated for class of 24 CPA II students.
    cpaII112019956.png
    Standard error (0.0190) (0.034) (0.018)
    Where y=students score on a theory examination
    x1 = Students rank (from the bottom) in high
    school x2 = Students verbal aptitude score
    x3 =A measure of students character
    Required:
    a) Calculate the t ratio and the 95% confidence interval for each regression coefficient.
    b) What assumptions did you make in (a) above? How reasonable are they?
    c) Which regressor gives the strongest evidence of being statistically discernible?
    d) In writing up a final regression equation, should one keep the first regressor in the equation, or drop if?
    Why?

    Date posted: January 1, 2019 .    Answers (1)

  • Unlisted plc hopes to achieve a Stock Market quotation for its shares. A profit forecast is necessary and, in order to achieve such a forecast,... (Solved)

    Unlisted plc hopes to achieve a Stock Market quotation for its shares. A profit forecast is necessary and, in order to achieve such a forecast, the company has experimented with a number of approaches. The following are details from a linear regression on the last 11 years profit figures:
    x = years (expressed 1 to 11)
    y = annual profit figures
    unlistedplc1412503.png
    You are required:
    a) To obtain the simple least squares regression line of Y on X;
    b) To use the line to estimate profit in each of the next two years;
    c) To calculate the coefficient of determination for the line and to explain its meaning;
    d) To calculate the standard error of the regression line and to use this to obtain the 95% confidence
    interval for the line;
    e) On the basis of the information given on your answer (a) to (d) to determine whether it is likely that the regression line will be a good estimator of profit.

    Date posted: December 14, 2018 .    Answers (1)

  • Two different models are available for the same machine. The production statistics (number of units produced per hour) of these two models are given below. The... (Solved)

    Two different models are available for the same machine. The production statistics (number of units
    produced per hour) of these two models are given below. The data was collected on different days.
    prodstats812819.png
    Will you conclude that Model A and Model B have the same productivity?

    Date posted: December 8, 2018 .    Answers (1)