Consider the following project network and activity times (in weeks) Required: i) How long will it take to finish this project? ii) Can activity D be delayed without...

Consider the following project network and activity times (in weeks)
act120220191126.png

Required:
i) How long will it take to finish this project?
ii)Can activity D be delayed without delaying the entire project? If so, by how many weeks?
iii)What is the schedule for activity E?

Answers


Wilfred
The activity on node network can be changed to event on node for ease of seeing the critical path. This also reduces the number of nodes encountered
act220220191128.png

i) The project will take 22 weeks to complete.
ii) Activity D cannot be delayed without delaying the entire project, since it is an activity in the critical path A-D-F-H.
iii) Activity E can start as early as after 3 weeks and can be delayed for one week without delaying the project time.
Wilfykil answered the question on February 20, 2019 at 07:29