Sixty people were hired to complete construction of a road in 6 days. Forty of the people did not turn up. How many more days...

Sixty people were hired to complete construction of a road in 6 days. Forty of the people did not turn up. How many more days did it take the remaining people to complete the construction?

A. 24
B. 18
C. 12
D. 3

Answers


Wilfred
The correct answer is [C]

1563183078962-q3115720191230.png
Wilfykil answered the question on July 31, 2019 at 05:58