Get premium membership and access questions with answers, video lessons as well as revision papers.
Got a question or eager to learn? Discover limitless learning on WhatsApp now - Start Now!

What is activity sequencing?

      

What is activity sequencing?

  

Answers


Francis
- identifying and documenting the logical and sometimes physical relationships among schedule activities
- Involves identifying and documenting the logical and sometimes physical relationships among schedule activities.
- there are 3 types of dependencies:
(i). Mandatory dependencies: inherent in the nature of the work; write software and then test
(ii). Discretionary dependencies: defined by the project team offer the most flexibility;
(iii). External dependencies: based on work being performed by an entity outside of the organization
- You must determine correct dependencies to create a realistic schedule
francis1897 answered the question on March 13, 2023 at 13:21


Next: State the activity characteristics
Previous: How can you develop a project schedule?

View More Management of IT Projects Questions and Answers | Return to Questions Index


Learn High School English on YouTube

Related Questions