Get premium membership and access questions with answers, video lessons as well as revision papers.
Got a question or eager to learn? Discover limitless learning on WhatsApp now - Start Now!

State some of the techniques used for shortening a project schedule (Schedule Analysis)

      

State some of the techniques used for shortening a project schedule (Schedule Analysis)

  

Answers


Francis
Knowing the critical path helps you make schedule trade-offs
(i). Shortening durations of critical tasks by adding more resources or changing their scope
(ii). Crashingtasks by obtaining the greatest amount of schedule compression for the least incremental cost
(iii). Fast tracking tasks by doing them in parallel or overlapping them
francis1897 answered the question on March 14, 2023 at 07:31


Next: Define the methods used to find the critical path
Previous: State the importance of updating critical path data

View More Management of IT Projects Questions and Answers | Return to Questions Index


Learn High School English on YouTube

Related Questions