Get premium membership and access questions with answers, video lessons as well as revision papers.
Got a question or eager to learn? Discover limitless learning on WhatsApp now - Start Now!

What are the resource leveling activities?

      

What are the resource leveling activities?

  

Answers


Francis
(i). Move activities – manually move activities by changing the discretionary dependencies or entering hard dates
(ii). Split – manually split activities such that only part of the activity is done at one time
(iii). Reduce resource availability – change the resource so they are not working full time on the task which will have the effect of lengthening the activity duration
(iv). Change/add resources to the task
(v). Authorizing the resource to work overtime
francis1897 answered the question on March 14, 2023 at 07:53


Next: Describe the resource loading and leveling as a tool used for schedule development
Previous: How can you level benefits?

View More Management of IT Projects Questions and Answers | Return to Questions Index


Learn High School English on YouTube

Related Questions