Vick Press Ltd is planning to expanding into offering security systems in people?s homes scared of security.The following are activities and associated costs for the expansion:

Vick Press Ltd is planning to expanding into offering security systems in people‟s homes scared of security.The following are activities and associated costs for the expansion:
vic12022019136.png

Required:
i) Determine the critical path.
ii) Determine the minimum time and minimum cost for the networks.
iii) Given that, for every delay beyond 40th week, there is share of Sh.1,000 per week loss of profit. Is it advisable to crash the project from 51 to 45 weeks? Why?

Answers


Wilfred
vic22022019138.png
vic32022019138.png
Wilfykil answered the question on February 20, 2019 at 09:39