Describe the process of creating a sample activity-on-arrow (AOA) network diagram

      

Describe the process of creating a sample activity-on-arrow (AOA) network diagram

  

Answers


Francis
1. You draw the first Begin circle or node and then proceed with the tasks that do not have a predecessor, usually the first tasks to be done on the project. These are shown in the diagram as lines A, K, and F
2. Then you move to the next tasks listed in the WBS in order of precedence. Activity B has a predecessor of A and Activity
C has a predecessor of B and so on. Tasks M, G, and L have no successors so we draw their arrows to the End node
3. You add circles at the end of each arrow as an end point. At the end of the process you then number each circle
4. Be prepared as you draw this diagram to draw and then erase and redraw as you work your way down the task list
5. You may need to add dummy activities to complete the diagram
francis1897 answered the question on March 13, 2023 at 13:52


Next: Describe the Arrow Diagramming Method (ADM) of activity sequencing
Previous: Describe the precedence diagramming method (PDM)

View More Management of IT Projects Questions and Answers | Return to Questions Index