Get premium membership and access revision papers, questions with answers as well as video lessons.

Ebc 3322: Measurement Of Civil Engineering Works Question Paper

Ebc 3322: Measurement Of Civil Engineering Works 

Course:Certificate In Construction Technician

Institution: Technical University Of Mombasa question papers

Exam Year:2011



SECTION A (COMPULSORY)
Question 1(30 marks)
Drawing No 01 shows a section and plan of a Mass Concrete Retaining wall 120M long. Take off all
quantities for Concrete and associated works but excluding Earthworks (30 marks)
SECTION B (Answer any TWO questions from this section)
Question 2 (20 marks)
Take off all quantities for the site clearance and demolition works shown in drawing no. 02
(Use CESMM) (20 marks)
Question 3 (20 marks)
a) Sate FOUR classes of Method Related Charges and list TWO items in each class differentiating
between fixed and time related charges (10 marks)
b) List and give brief explanation of FIVE merits of Piling Ancillaries (10 marks)
Question 4 (20 marks)
A cutting is to be excavated for a road 240 M in length and 12 M in wiedth, to an even gradient with
mean depths calculated at 60 M intervals as indicated below and side slopes 2 to 1. General material
for disposal
a) Prepare a detailed table for the cutting including the calculations for the mean width (10 marks)
b) Take off quantities for the excavations (Use CESMM) (10 marks)
CROSS SECTION 1 2 3 4 5
MEAN DEPTH (M) 11 10 16 18 17
Question 5 (20 marks)
Drawing no.03 shows a section through a Quay 108m long. Take off quantities for the Piling Works
only up to and including piling ancillaries (Use CESMM) (20 marks)